Order Item:
4042% PLAQUETTES 230X114X38 2973 PCS  
4042% BRIQUES 230X114X64 1842 PCS  
4042% BRIQUES 230X114X76 6963 PCS
GR30 230X114X64 61 PCS  
GR30 230X114X76 1745 PCS  
GR23 440x340x50 1 PCS  
GR23 440x275x50 1 PCS  
GR23 230X114X76 3080 PCS
…

ORDER CONFIRM

THE ORDER CONFIRMED : 29/09/2025

FIREBIRCKS

THE BIRCKS FINISH COMPRESSION MOULDING TIME OCT.05,
FINISH DRYING TIME OCT.15,
ALL FINISH OCT.29

INSULATING BIRCKS

THE BIRCKS DRYING TIME FROM OCT. 05 TO OCT.23 ,
HEAT  TREATMENT TIME FROMOCT. 23 TO OCT.30 ,
CUTTING AND POLISHING FINISHED NOV.03

INSULATING BIRCKS DRYING

INSULATING BIRCKS DRYING

INSULATING BIRCKS FIRING

INSULATING BIRCKS MID FINISHED BLOCK

OCT.05 4042% PLAQUETTES 230X114X38

The bricks have finished press procerss to proceed the dry process.

OCT.15, 4042% BRIQUES 230X114X64

The bricks have finished dry process to proceed the firing process.

OCT.15 4042% BRIQUES 230X114X76

The bricks have finished dry process to proceed the firing process.

OCT.29 4042% PLAQUETTES 230X114X38

OCT.29 4042% PLAQUETTES 230X114X38 have been finished and passed inspection.

OCT.29, 4042% BRIQUES 230X114X76

OCT.29, 4042% BRIQUES 230X114X76 have been finished and passed inspection.

NOV.03,GR23 230X114X76

NOV.03,GR23 230X114X76 have been finished and passed inspection.

NOV.03,GR30 230X114X64

NOV.03,GR30 230X114X64 have been finished and passed inspection.

NOV.03,GR30 230X114X76

NOV.03,GR30 230X114X76 have been finished and passed inspection.

TEST REPORT

TEST REPORT

TEST REPORT

TEST REPORT

NOV 19, LOADING CONTAINER BXVU0013510

NOV 19, CONTAINER have been loaded.

NOV 19, LOADING CONTAINER BXVU0014080

NOV 19, CONTAINER have been loaded.

NOV 19 , SHIPMENT SCHEDULE

BL NO.:QGD2387293
M/V:CMA CGM PALAIS ROYAL /0FML8W1MA
ETD: NOV 24,  2025
ETA: JAN 07,  2026